Phase 3 of Ksh2.3b Ngong Road Upgrade in Kenya to be Completed in May 2021
The 9.8km road project has been under construction since July 2017, and was initially scheduled for completion in 2019.
But that didn’t go as planned due to some challenges in moving water and power lines encountered by the contractor. The presence of furniture traders who had invaded the road section was also another cause for delay.
The contract for the KES 2.3bn project was awarded to a Chinese firm, Quinjian